Asphalt Project 2022 - August 31, 2022

Asphalt, curb, and sidewalk project


September 2, 2022


The board has recently awarded the contract to replace all common area asphalt and repair damaged curbs and sidewalks, to Metro Asphalt. This work is anticipated to start on September 19th (weather permitting).


During this project, which should take approximately 10 business days (weather permitting), access to some homes may be unavailable. Town of Oakville street parking passes are being applied for and will be distributed no later than September 16th.


The project will be split into give components:

1) Curbs repair/replacement *

2) Sidewalk repair/replacement *

3) New asphalt in drivelane of the first half of the project

4) New asphalt in other half of the project & the addition of speed bumps

5) Line marking


*Not all curbs and sidewalks are being replaced, only ones that have been identified and approved by the board. This work will also include the removal of the small islands in visitor parking, which will allow us to add one additional parking space.

While this work is underway, we ask that all residents be mindful of the construction vehicles. If you have any concerns, you may contact either the lead foreman at Metro, or management

.Metro Asphalt Notice